QUESTION 35
You have successfully configured an InfraStruxure solution. Th Detailed Quote Report lists a 30 kw three-
phase UPS which you know is oversized based on the project’s requirements.
Which two fields in the Build Out Tool can be adjusted to reduce the size of the UPS?

A. SYSTEM voltage and system KVA
B. Watts per rack and number of racks
C. Battery runtime and number of whips
D. System redundancy and battery runtime

Correct Answer: B
QUESTION 36
You are configuring an Infrastruxure solution using the Build Out Tool. You have sized the area specific to
the total number of enclosure that required including UPS and PDU. You enter 60 minutes of battery
runtime and the following message appears.